Construction example

Asao-ku, Kawasaki | Performed roof overlay (cover method) by Ridgeway and removed skylights!

BEFORE

AFTER

Hello!
I am Yamanaka from Kakeru Koumuten Co., Ltd., a specialist in roofing, exterior wall painting, and exterior renovations located in Aoba-ku, Yokohama, Kanagawa Prefecture!
This is a case study of an exterior renovation project in Asao-ku, Kawasaki City.
The work this time includes roof overlay (cover method) using Ridgeway and the removal of a skylight!

This apartment had four skylights, but due to a leak from one of them, we received a request to remove it, and we proceeded with the removal!

On this page, I will explain the actual results of the work done by Kakeru Koumuten!

Thank you very much for choosing Kakeru Koumuten Co., Ltd. from among many contractors.

Roof Overlay (Cover Method) Construction Steps

1. Removal of Existing Ridge Cap and Skylight


We will dismantle the existing ridge and snow stops that are unnecessary for the cover method! Since we are removing one skylight this time, we will also take out the skylight!

2. Repair of Skylight Underlayment

We will cover the area where the skylight was removed with plywood. We will adjust it to match the height of the existing roofing material. Since it may look unsightly from inside if it remains as plywood, we sometimes apply wallpaper.

3. Installation of Roofing (Waterproof Sheet)

Next, we will install the roofing sheet (waterproof sheet)! The roofing used is Tajima Roofing/Tadis Self!
This material is a delayed adhesive modified asphalt roofing, which is said to have double the durability of regular asphalt roofing.
Due to its adhesive properties, it sticks to the substrate, providing higher waterproofing compared to standard roofing.
As a primary waterproofing measure, if the roofing is properly installed, there will be no leaks!
We will ensure it is securely adhered to prevent it from blowing away.

4.Accessory Processing (Karakusa and Keraba)

Before the main roof construction, we will process and install accessories such as keraba and karakusa sheet metal!
The materials used for the accessories will be galvalume steel sheets.

5.Main Construction (Asahi Fiberglass/Ridgeway)

After processing the accessories, we will install the Ridgeway main roofing up to the ridge! We will apply single cement at the overlapping areas during the installation.
Once we have installed up to the ridge, we will place the necessary materials called “kanban” to secure the ridge metal.

6. Skylight Surrounding Sheet Metal Processing

Simultaneously with the main construction of the Ridgeway, we will process the sheet metal around the skylight. We will be working with flat sheet metal made of galvalume.

7. Ridge Metal and Sealing at Various Locations

Next, we will process and install the ridge cap. We will thoroughly apply sealing on the inside of the joints. We will also perform waterproof sealing around the skylight.
We will use stainless steel nails and screws that are resistant to rust!

8. Cleaning


We will clean up the debris that has fallen onto the balcony and rain gutters. We will thoroughly remove any nails or metal fragments to prevent injuries. The balcony will be restored to its original state, marking the completion of the work!

About Roofing Material (Ridgeway)

The roofing material used is Ridgeway from Asahi Fiberglass.
Ridgeway comes with a 10-year manufacturer warranty.
Since it uses natural stone that is baked onto the surface, it is a roofing material that does not require painting, thus reducing maintenance costs!
The use of fine natural stones on the surface means you won’t be troubled by rain noise.
Additionally, it is a lightweight roofing material, making it strong against earthquakes and providing seismic resistance.

*After installation, the surface decorative stones may fall off for about a week, but this does not indicate any quality issues.

Colors

■ Dual Black
Ridgeway Black

■ Harvard Slate
Ridgeway Harvard Slate

■ Vintage Green
Ridgeway Green

■Dual Brown
Ridgeway

■Earthtone Cedar

Ridgeway Earthtone Cedar

This time, we completed a roof construction with Dual Black, and it turned out exceptionally well!
The customer was very satisfied, and I was also very happy!
Thank you very much!

Please check out other roofing construction achievements from here!

What is the Roof Overlay (Cover Method)?

The roof overlay method involves leaving the current roof almost as it is and placing a new roof on top of it, effectively covering it.
Literally, it is a method of covering a roof with another roof. Therefore, the roof becomes double-layered. Since the roof is laid over, it is also referred to as “overlapping roofing.”

Advantages of the Overlay Method

Since a “new roof” is placed over the “current roof,” almost no demolition work is required, meaning very little waste is generated.
This is its biggest feature, leading to various advantages.

The only part that requires demolition and waste disposal is the ridge cap, making it more cost-effective compared to complete roof replacement.
In 2004, regulations regarding the concentration of asbestos in raw materials were changed (for details, please refer to the Ministry of Health, Labour and Welfare’s website).
Some building materials used in structures built before 2004 contain asbestos. Asbestos-containing materials are difficult to demolish due to their high environmental impact, and the costs for demolition and waste disposal are also high. The overlay method, which generates almost no waste, is ideal for such roofs.

Some may wonder, “Is it safe to live in a building that uses asbestos-containing materials?” but rest assured. As long as there is no destruction or crushing, it will not disperse into the air.
If you are unsure about the type of roof on your home, please feel free to consult us.

Additionally, it can be completed in a shorter time frame compared to painting or complete replacement. A shorter construction period means lower labor costs, which in turn makes the expenses more affordable.
The psychological anxiety of having to live in an unusual environment is also reduced.
When scaffolding is set up, there may be inconveniences such as difficulty entering and exiting or opening windows. Being able to return to normal life in a short period is a significant advantage.

Our company specializes in roofing work, and the roof overlay method is the most frequently performed type of work we undertake. We are very grateful that we continuously receive requests for roof overlay method construction without interruption.

Roof Material

Asahi Fiberglass/Ridgeway

Fiberglass Ridgeway
Manufacturer Warranty 10 years
Expected Durability 25 to 30 years
Color Used This Time

Dual Black

Ridgeway Black

Leave Your Roof Renovation in Asao-ku, Kawasaki to Kakeru Koumuten!

Our company has extensive experience in roof renovations in Asao-ku, Kawasaki.
We are happy to assist with partial roof repairs, including roof overlay work, roof replacement, and leak repairs.
If you have any questions or concerns, such as “I just want to know the estimate for the roof renovation” or “I want to know about roofing materials,” please feel free to contact us!

Community-Focused Service

As a home exterior renovation company based in Aoba-ku, Yokohama, we have handled many roof renovations in nearby Asao-ku, Kawasaki, and we deeply understand the needs of local customers.

I want it to last a long time with just one renovation

I want to keep costs as low as possible

I want to improve insulation performance because the indoors are hot

We provide optimal solutions for specific requests like this.

Summary

Estimates and inspections are, of course, free! If you have any concerns regarding roofs, rain gutters, exterior walls, or exteriors, please consult Kakeru Koumuten Co., Ltd. in Aoba-ku, Yokohama!

Kakeru Koumuten is a remodeling company strong in exterior renovations, and we conduct complete in-house construction from temporary scaffolding to roof work and exterior painting.
We are confident that our “cost, quality, and good organization” are unmatched compared to other companies when it comes to exterior renovation work!

We are confident in our exterior renovations, so we welcome competitive estimates!
We offer comprehensive construction guarantees and aftercare maintenance, and we have received positive feedback for our appropriate proposals that match cost performance and our customers’ future life plans!

“I’m glad I asked them!” We take every request seriously to ensure you feel this way.

We also have information on roofing costs and pricing plans for the roof overlay (cover method), so please take a look if you’re interested!

We look forward to your inquiries. Thank you very much.

Helpful information about exterior renovations can be found here!

LINE consultations are also very welcome◎

We are regularly updating our Instagram◎Please follow us, thank you◎

For roofing, guttering, and exterior work and repairs in Kanagawa, contact Kakerukoumuten Co., Ltd..

AAA is a young company with an average age in the early 20s, but our technology is second to none.

One of our greatest strengths is that we can do all of our own scaffolding, roofing, and painting work. In this industry, where work is generally divided, we are able to provide a complete set of services, which saves time and effort in management and reduces costs. Above all, if there is any trouble, we will come to you right away!

We can confidently declare this. We are the youngest and most friendly renovator in Kanagawa!