- 1 Construction Data for Zushi City, Kanagawa Prefecture
- 2 Roof Overlay Construction Photos
- 2.1 1. Removal of Solar Panels
- 2.2 1. Demolition of Existing Ridge Flashing and Purlins
- 2.3 2. New Sheathing Installation
- 2.4 3. Roofing Installation (Waterproof Sheet)
- 2.5 4. Custom Fabrication (Kera and Karakusa)
- 2.6 5. Main Construction (Inagaki Shouji/Hiranbee)
- 2.7 6. Ridge Cap Processing and Sealing
- 2.8 7. Cleaning
- 2.9 About Roofing Materials
- 2.10 Color
- 3 What is the Roof Overlay (Cover Method)?
- 4 For Roof Renovations in Zushi City, Kanagawa, Trust Kakeru Koumuten!
Construction Data for Zushi City, Kanagawa Prefecture
| Construction Location |
| Zushi City, Kanagawa Prefecture |
| Construction Details |
| Temporary scaffolding installation Roof overlay construction Solar panel removal and reinstallation |
| Inquiry Details |
|
We received an inquiry from a customer living in Zushi City, Kanagawa Prefecture. |
| Price Range |
| 800,000 to 900,000 yen |
| Construction Period |
| About 1 week |
| Completion Month |
| October 2024 |
Roof Overlay Construction Photos
1. Removal of Solar Panels
1. Demolition of Existing Ridge Flashing and Purlins
2. New Sheathing Installation

3. Roofing Installation (Waterproof Sheet)

This material is modified asphalt roofing, which is said to have double the durability of regular asphalt roofing.
With the roofing properly installed as a secondary waterproofing measure, there will be no leaks!
We will ensure it is firmly attached to prevent it from blowing away!
4. Custom Fabrication (Kera and Karakusa)
The materials used for the custom pieces are galvalume steel.
5. Main Construction (Inagaki Shouji/Hiranbee)
Once the roofing is completed up to the ridge, we will install the necessary materials to secure the ridge cap, known as purlins. There are types of purlins made of cedar, resin, and galvalume steel, and this time we used the resin type!
The resin type is expected to have twice the durability of the cedar type!
6. Ridge Cap Processing and Sealing
The nails and screws used for fixing are made of stainless steel, which is resistant to rust!
7. Cleaning
About Roofing Materials
The roofing material used is Hiranbee 220 from Inagaki Shouji.
Hiranbee 220 comes with a manufacturer warranty of 15 years for the coating and 25 years for perforation.
For re-roofing and overlaying, we also provide a construction warranty of 10 years!
If there are any leaks within 10 years, we will make repairs free of charge.
It is made of Galvalume steel, which is also resistant to rust.
The formed panels have been treated with iris folds and wave processing to prevent distortion and enhance strength, as well as improve water drainage and aesthetic effects.
Additionally, it excels in finish, durability, sound insulation, and wind resistance, and because it is lighter compared to other roofing materials, it reduces the sway during earthquakes, making it a good earthquake countermeasure.
In the overlay (cover) work we performed this time, the roof becomes double-layered, which increases the weight, but Hiranbee is a lightweight roofing material, making it suitable for overlay (cover) work.
Color
Extreme – MAX Type
■ Gray Silver

■ Silver Black

■ Sepia

■ Moss Green

■ Bamboo Green

■ Midnight Blue

■ Jet Black

■ Dark Brown

■ Bright Red

Standard Type
■ Steel Black
■Marron Brown

■J Silver

You can choose from these options!
This time, we completed a roof replacement project with Silver Black, and it turned out exceptionally well!
Thank you for your request!!
Please check out other roofing project results here!
What is the Roof Overlay (Cover Method)?
The roof overlay construction method involves leaving the existing roof largely intact and placing a new roof on top of it, effectively covering it.
As the name suggests, it is a method of covering a roof with another roof. Therefore, the roof becomes double-layered. This method is also referred to as “overlapping roofing.”
Benefits of the Overlay Method
Since a “new roof” is placed over the “existing roof,” there is almost no need for demolition work, meaning very little waste is generated.
This is its most significant feature, leading to various advantages.
The only part that requires demolition and waste disposal is the ridge cap, making it more cost-effective compared to full roof replacements.
In 2004, regulations regarding the concentration of asbestos in raw materials were changed (for details, please refer to the Ministry of Health, Labour and Welfare’s website).
Some building materials used in structures built before 2004 contain asbestos. Asbestos-containing materials are difficult to demolish due to their high environmental impact, resulting in high costs for both demolition and waste disposal. The overlay method, which generates almost no waste, is ideal for such roofs.
Some may wonder, “Is it safe to live in a building with asbestos-containing materials?” Rest assured, as long as there is no destruction or crushing, it will not disperse into the air.
If you are unsure about the type of roof on your home, please feel free to consult us.
Additionally, the construction can be completed in a shorter timeframe compared to painting or full roof replacements. A shorter construction period means lower labor costs, which in turn reduces overall expenses.
The psychological anxiety of having to live in an unusual environment is also minimized.
When scaffolding is set up, you may experience inconveniences such as difficulty entering and exiting or being unable to open windows. Being able to return to your normal life in a short period is a significant advantage.
Our company specializes in roofing work, and the roof overlay method is the most frequently performed type of construction we undertake. We are very grateful that we consistently have ongoing projects for roof overlay construction.
The Necessity of Roof Work (Roof Repair) and Maintenance Schedule
◇ Necessity and Maintenance of Roof Work and Roof Repair
・Necessity and Purpose of Roof Work
The roof is directly exposed to damage from rain, wind, and ultraviolet rays, and issues such as cracks and leaks become apparent over time. By carrying out roof work, the durability of the building is enhanced, maintaining a comfortable living space. Additionally, improvements in energy efficiency can be expected. For example, using highly insulating roofing materials can lead to reduced heating and cooling costs.
In terms of long-term cost performance, roof work can be considered an important investment.
・Schedule for Roof Work (Roof Repair)
Depending on the type of roofing material and the local climate, roof work (roof repair) is generally carried out every 10 to 15 years. After that, inspections should be conducted approximately every five years, with repairs or painting performed as necessary. Regular maintenance allows for early detection of minor deterioration or damage, which can reduce the risk of large-scale construction or repairs.
However, this is merely a guideline, and the timing can vary based on the material of the roof and environmental conditions such as high temperatures, humidity, strong winds, and snowfall. Under severe weather conditions, more frequent checks may be necessary. Additionally, roof work (roof repair) involves working at heights, so it is advisable to hire a professional contractor.
Post-Construction Maintenance
◇ Importance of Post-Construction Maintenance
Maintenance after exterior painting and roof repair is a crucial factor in extending the lifespan of the home. Neglecting maintenance can lead to rapid deterioration of newly painted exteriors and repaired roofs, resulting in the risk of incurring high costs. The exterior walls and roof of a building are constantly exposed to harsh natural environments such as rain, wind, ultraviolet rays, and temperature changes. Regular maintenance minimizes damage and helps maintain the home’s aesthetics and comfort. Additionally, it can help avoid large-scale repair work and the associated significant expenses.
◇ Maintenance Methods and Frequency
For post-construction maintenance, inspections by professional contractors are effective. This allows for early detection and repair of even minor damage. The recommended frequency for maintenance is generally exterior painting every five years and roof repair every three years. This is only a guideline and may vary based on local climate conditions and the structure of the home.
| Roofing Material |
|
|---|---|
| Manufacturer Warranty | 15 years for coating / 25 years for perforation |
| Expected Durability | Approximately 35 years |
| Color Used This Time | Dark Brown![]() |
For Roof Renovations in Zushi City, Kanagawa, Trust Kakeru Koumuten!
Our company has extensive experience in roof renovations in Zushi City, Kanagawa.
We are happy to assist with partial roofing work, including roof overlay projects, roof replacements, and leak repairs.
If you have any questions or concerns, such as “I just want to know the estimate for roofing work” or “I want to know about roofing materials,” please feel free to contact us!
List of Areas in Zushi City, Kanagawa
Ikezoe, Zushi City / Kotsubo, Zushi City / Sakurayama, Zushi City / Shinjuku, Zushi City / Zushi, Zushi City / Numama, Zushi City / Kuki, Zushi City / Yamanone, Zushi City
Long-Term Reliability
All roofing materials we use are reliable products that offer long-term warranties. For example, the Hiranbee 220 from Inagaki Shoji that we used this time comes with a 15-year coating warranty and a 25-year perforation warranty, allowing you to use it with peace of mind for a long time after a single renovation.
Hiranbee is a lightweight roofing material that excels in durability and cost performance, but we also offer roofing materials with even higher durability and better insulation properties.
Conclusion
Estimates and inspections are, of course, free! If you have any concerns regarding roofs, rain gutters, exterior walls, or exteriors, please consult Kakeru Koumuten Co., Ltd. in Aoba-ku, Yokohama!
Kakeru Koumuten Co., Ltd. is a remodeling company strong in exterior renovations, and we carry out everything from temporary scaffolding work to roof work and exterior painting work completely in-house.
When it comes to exterior renovation work, we are confident that we do not fall short compared to other companies in terms of “cost, quality, and efficiency”!
We are confident in our exterior renovations, so we welcome competitive estimates!
We offer robust construction guarantees and aftercare maintenance, and we have received positive feedback for our appropriate proposals that align with cost performance and our customers’ future life plans!
“I’m glad I asked them!” We take every request we receive seriously to ensure you feel this way.
We also have information on roof construction costs and pricing plans for the roof overlay (cover method), so please take a look if you are interested!
We look forward to your inquiries. Thank you very much.
Helpful information about exterior renovations can be found here!
・【Zushi City, Kanagawa】|After-Sales Maintenance|First-Year Inspection Completed!
・【Zushi City, Kanagawa】|Exterior Wall Painting|Completed Heat-Reflective Coating and Joint Replacement Work!
・【Zushi City, Kanagawa】Exterior Wall Painting, Joint Sealing Work, and Roof Repair Work Completed!
・Popular Colors for Exterior Wall Painting! Introducing Recommended Color Combinations!
・DIY Painting Plan! A Must-See for Those Who Want to Try DIY Roof and Exterior Wall Painting! We Only Set Up Scaffolding!
・About the Costs of Roof Overlay|Kakeru Koumuten’s Roofing Plans!
・About the Costs of Exterior Wall Painting|Kakeru Koumuten’s Exterior Wall Painting Plans!
・About the Costs of Leak Repairs|Kakeru Koumuten’s Leak Repair Plans!
・About the Costs of Ridge Cap Replacement and Surface Plaster|Kakeru Koumuten’s Construction Plans!
・Latest Information|Subsidies and Grants Available for Renovations!
・What are the market prices for rain gutter repair and cleaning? Tips on timing, fire insurance, and choosing a contractor!
・Renovation store in Kanagawa Prefecture, Yokohama | What is roof overlay (roof cover method)?
Consultations via LINE are also very welcome◎
AAA is a young company with an average age in the early 20s, but our technology is second to none.
One of our greatest strengths is that we can do all of our own scaffolding, roofing, and painting work. In this industry, where work is generally divided, we are able to provide a complete set of services, which saves time and effort in management and reduces costs. Above all, if there is any trouble, we will come to you right away!
We can confidently declare this. We are the youngest and most friendly renovator in Kanagawa!